7.15.2022 Notice of Street Construction: Route 355 & Walker Ave. between Brookes Ave. & Chestnut St.

分享到Facebook(另開新視窗) 分享到twitter(另開新視窗) 分享到微信(另開新視窗)  

Gaithersburg, MD (July 12, 2022) Beginning, Sunday, July 17, 2022, at approximately 8 p.m., Alpha Space Control, working for the City of Gaithersburg, will perform safety improvements to striping, signage and channelizing curb with delineators. The work will take place between Brookes Avenue and Chestnut Street on Maryland Route 355 (North Frederick Avenue) and Walker Avenue in the City of Gaithersburg.

The following are the hours planned for the work:

• Sunday, July 17, 8 p.m. to 5 a.m.

• Monday, July 18, 9 a.m. to 3 p.m.

• Tuesday, July 19, 9 a.m. to 3 p.m.

Weather and progress permitting, all work is expected to be completed no later than Friday, July 22, at 3 p.m.

In case of inclement weather, the work will continue on Wednesday, July 20, ending Friday, July 22, 2022. Work during this time period will be from 9 a.m. to 3 p.m.

To complete this work, crews are permitted to close the inner lanes northbound and southbound and the turn lane northbound at Chestnut Street on MD 355 (North Frederick Avenue) within the project limits during the construction time period.

For questions regarding this work, please contact Mark Kile, City of Gaithersburg Project Manager, at 240-805-1322 or mark.kile@gaithersburgmd.gov.